Construction Updates

Printed Thu Dec 12 2019 16:09:32 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with floor and wall tiles, waterproofing, wall plastering, ceiling work, installing handrails on the balconies, beam installation for elevators, brick wall installation, rebar and I-beam installation for decking.

NaN/10

Bali Water World A
Bali, Indonesia

     1. Structural Works
          - Building A : 98%
          - Lower Ground Floor & Pool  : 43%
     2. Architectural Works
          - Building A  : 36%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 34%

NaN/6

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Building B : 98%
          b. Lower Ground Floor & Pool  : 43%
      2. Architectural Works
          a. Building B  : 40%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 45%

NaN/5

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Building C : 98%
         b. Lower Ground Floor & Pool : 43%
      2. Architectural Works
          a. Building C : 41%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 31%

NaN/6

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 98%
     2. Architectural Works
          a. Building D : 94%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 75% 

NaN/5

Bali Water World E
Bali, Indonesia

   1. Structural Works
         a. Building E : 100%
         b. Pool : 98%
     2. Architectural Works 
         a. Building E : 76%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 72%

NaN/5